|
|
A blog of all sections with no images
|
Frequency of Tests |
|
|
Recommended Initial Frequencies of Inspection of Electrical Installations.
| Type of Installation |
Routine check
sub clause 3.5 |
Maximum period between Inspections
and testing as necessary |
Reference
see notes
below. |
General Installation
|
Domestic
Commercial
Educational establishments
Hospitals
Industrial
Residential accommodation
Offices
Shops
Laboratories |
See Sellers pack law
1 year
4 months
1 year
1 year
change of occupancy / 1 year
1 year
1 year
1 year |
change of occupancy/10 years
change of occupancy/5 years
5 years
5 years
3 years
5 years
5 years
5 years
5 years |
0.0
1.2
1.2
1.2
1.2
1.0
1.2
1.2
1.2 |
Buildings open to the public.
|
| Cinemas |
1 year
|
3 year
|
2,6,7 |
| Church installations |
1 year
|
5 years |
2 |
Leisure complexes(no pools)
|
1 year
|
3 years |
1,2,6 |
Public entertainment
|
1 year
|
3 years |
1,2,6 |
Restaurants / Hotels
|
1 year
|
5 years |
1,2,6 |
Theatres
|
1 year
|
3 years |
2,6,7 |
Public houses / Bars
|
1 year
|
5 years |
1,2,6 |
| Village hall / centres |
1 year |
5 years |
1,2 |
Special Installations
|
| Agricultural / Horticultural |
1 year |
3 years |
1,2 |
| Caravans |
1 year |
3 years |
0.0 |
| Caravan Parks |
6 Months |
1 year |
1,2,6 |
| Highway power supplies |
as convenient |
6 years |
0.0 |
| Marinas |
4 Months |
1 year |
1,2 |
| Fish farms |
4 Months |
1 year |
1,2 |
| Swimming pools |
4 Months |
1 year |
1,2,6 |
| Emergency lighting |
Daily / Monthly |
3 years |
2,3,4 |
| Fire Alarms |
Daily/weekly/monthly |
1 year |
2,4,5 |
| Laundrettes |
1 year |
1 years |
1,2,6 |
| Petrol stations |
1 year |
1 year |
1,2,6 |
| Construction sites |
3 Months |
3 Months |
1,2 |
Reference Key:
|
| 1. Particular attention must be taken to comply with SI 1988 No1057. The electricity supply regulations 1988(as amended) |
| 2. SI 1989 No 635. The electricity at work regulations 1989 (Regulation 4 & memorandum). |
| 3. See BS 5266: Part1: 1988 Code of practice for the emergency lighting of premises other than cinemas and certain other specified premises used for entertainment. |
| 4. Other intervals are recommended for testing operations of batteries and generators. |
| 5. Se BS5839:Part1: 1988 Code of practice for system design installation and servicing (Fire detection and alarm systems for buildings). |
| 6. Local authority conditions of license. |
| 7. SI 1995 No 1129 (Clause 27) The cinematograph (Safety) Regulations. |
| |
|
|
|
Portable Appliance Testing |
|
|
Portable Appliance Testing (P.A.T.)
A portable appliance is classed as any piece
of equipment which can be connected to the common supply by
means of a plug and socket arrangement. It must be maintained to be safe at all times. In effect any electrical equipment that has a mains plug on it.
While performing the tests we normally repair or relace damaged plugs and fuses. Our test equipement is always in calibration and is suitable for IT work.
Once the testing is complete you will have :
- An asset list of all P.A.T. equipement
- All the test data for any local authority requirement
- A list of all Failures
- This data is available (members area) securely, both viewable and printable for our customers who have an account on this website.
- You will automatically receive a reminder when retesting is due. Timescale changes with individual clients.
|
|
|
Electrical Installation Testing. |
|
|
Electrical
Installation Testing
All aspects of the electrical installation
are inspected and tested for strength, integrity and compliance
with the IEE Regulations.
Any faults or defects found will be
recorded, and a suggested method for correcting the fault will be given to you. Upon completion of the tests a complete schedule of the tests will include the following.
- Periodic inspection certificate
- Detailed circuit assessment sheets
- Faults discovered while surveying
- Survey report specific faults, locations
& suggested solutions
- Laminated circuit schedules, as required
- Computer generated drawings
- Dangerous conditions report
Electrical Testing for Safety
|
|
|
The electrical tests part 2 |
|
|
8.6.1 - Testing earth electrodes
The earth electrode, where used, is the means of making
contact with the general mass of earth. Thus it must be tested to ensure that
good contact is made. A major consideration here is to ensure that the electrode
resistance is not so high that the voltage from earthed metalwork to earth
exceeds 50 V. Where an RCD is used, this means that the result of multiplying
the RCD operating current (in amperes) by the electrode resistance (in ohms)
does not exceed 50 (volts). for normal dry locations, or 25 (volts) for
construction sites and agricultural premises.
If a 30 mA RCD is used, this allows a maximum electrode
resistance of 1,666 Ohms, although it is recommended that earth
electrode resistance should never be greater than 200 Ohms.A maximum value of 100 ohm is proposed in a
draft amendment of BS 7430, Code of Practice for Earthing.
There are several methods for measurement of the earth
electrode resistance. In all cases, the electrode must be disconnected from the
earthing system of the installation before the tests commence.
Fig 8.13 - Measurement of earth electrode
resistance with a dedicated tester
1. - Using a
dedicated earth resistance tester
The instrument is
connected as shown in {Fig 8.13} with terminals C1 and P1 being connected to the
electrode under test (X). To ensure that the resistance of the test leads does
not affect the result, separate leads should be used for these connections. If
the test lead resistance is negligible, terminals Ci and P1 may be bridged at
the instrument and connected to the earth electrode with a single
lead.
Terminals C2 and P2 are connected to temporary spikes which
are driven into the ground, making a straight line with the electrode under
test. It is important that the test spikes are far enough from each other and
from the electrode under test. If their resistance areas overlap, the readings
will differ for the reason indicated in {Fig 8.14}. Usually the distance from X
to Y will be about 25 m, but this depends on the resistivity of the ground. To
ensure that resistance areas do not overlap, second and third tests are made
with the electrode Z 10% of the X to Y distance nearer to, and then 10% further
from, X. If the three readings are substantially in agreement, this is the
resistance of the electrode under test. If not, test electrodes Y and Z must be
moved further from X and the tests repeated.
The tester provides an alternating output to prevent
electrolytic effects. If the resistance to earth of the temporary spikes Y and Z
is too high, a reduction is likely if they are driven deeper or if they are
watered.
Fig 8.14 - Effect of overlapping resistance
areas
a) resistance areas not overlapping
b)
resistance areas overlapping
2. -
Using a transformer, ammeter and voltmeter
The system
is connected as shown in {Fig 8.15}. Current, which can be adjusted by variation
of the resistor R, is passed through the electrode under test (X) to the general
mass of earth and hence to the test electrode Y. The voltmeter connected from X
to Z measures the volt drop from X to the general mass of earth. The electrode
resistance is calculated from:
| voltmeter reading (V) |
| ammeter reading (A) |
As in the case of the dedicated tester, the test
electrode Z must again be moved and extra readings taken to ensure that
resistance areas do not overlap. It is important that the voltmeter used has
high resistance (at least 200 Ohms /V) or its low resistance in parallel with
that of the electrode under test will give a false result.
Fig 8.15 - Measurement of earth electrode
resistance
with a transformer, ammeter and voltmeter
3. - Using an earth fault loop impedance
tester
The tester is connected between the phase at
the origin of the installation and the earth electrode under test as shown in
{Fig 8.16}. The test is then carried out, the result being taken as the
electrode resistance although the resistance of the protective system from the
origin of the installation to the furthest paint of the installation must be
added to it before its use to verify that the 50 V level is not exceeded. If an
RCD with a low operating current is used, the protective system resistance is
likely to be negligible by comparison with the permissible electrode
resistance.
Fig 8.16 - Measurement of earth electrode
resistance using an earth-fault loop tester
It is most important to ensure that earthing leads and
equipotential bonds are reconnected to the earth electrode when testing is
complete.
8.6.2 - Measuring earth-fault loop impedance and
prospective short-circuit
current
The nature of the earth-fault loop and its significance have
been considered in detail in {5.3}. Since the loop includes the resistance of phase and
protective conductors within the installation, the highest values will occur at
points furthest from the incoming supply position where these conductors are
longest. A measurement within the installation will give the complete
earth-fault loop impedance far the point at which it is taken (Zs), or the
earth-fault loop impedance external to the installation (Ze) may be measured at
the supply position. Internal loop measurements should be taken at points
furthest from the intake to give the highest possible results.
In simple terms, the impedance of the phase-to-earth loop is
measured by connecting a resistor (typically 10 Ohms) from the phase to the
protective conductor as shown in {Fig 8.17}. A fault current, usually something
over 20 A, circulates in the fault loop, and the impedance of the loop is
calculated within the instrument by dividing supply voltage by the value of
this current. The resistance of the added resistor must be subtracted from this
calculated value before the result is displayed. An alternative method is to
measure the supply voltage both before and whilst the loop current is flowing.
The difference is the volt drop in the loop due to the current, and loop
impedance is calculated from voltage difference divided by
current.
Fig 8.17 - Simple principle of earth-fault
loop testing
Since the loop current is very high, its duration must be
short and must be limited to two cycles (or four half-cycles) or 40 ms for a 50
Hz supply. The current is usually switched by a thyristor or a triac, the firing
time being controlled by an electronic timing circuit It is very important to
have already checked the continuity of the protective system before carrying out
this test. A break in the protective system, or a high resistance within it,
could otherwise result in the whole of the protective system being directly
connected to the phase conductor for the duration of the test. Commercial
testers are usually fitted with indicator lamps to confirm correct connection or
to warn of reversed polarity. {Fig 8.18} shows a typical earth-fault loop tester
connected to a socket outlet so that its loop impedance can be measured. If the
circuit to be measured includes socket outlets, the tester is connected as
indicated in {Fig 8.18}. Special leads for connection to phase and to earth are
provided by suppliers for all other circuits.
Fig 8.18 - Earth-fault loop tester connected for
use
Before testing, the main equipotential bonding conductors are
disconnected (BUT NOT THE CONNECTION WITH EARTH) to prevent parallel earth
return paths and to ensure that there is no reliance on the service pies for gas
and water for effective earthing, (REMEMBER TO RECONNECT THE MAIN EQUIPOTENTIAL
BONDING AFTER THE TEST).
Tests must be carried out at the origin of the installation,
at each distribution board, at all fixed equipment, at all socket outlets, at
10% of all lighting outlets (choosing points farthest from the supply) and at
the furthest point of every radial circuit. The test should be repeated at least
once to allow for the effect of transient variations in the supply
voltage.
A modified version of the earth-fault loop tester, which
effectively measures the phase to neutral impedance and calculates then displays
the value of the current which would flow if the supply voltage were applied to
this impedance are readily available. The principle of such a PSC tester is
described in {3.7.2}.
Since the test result is dependent on the supply voltage,
small variations will affect the reading. Thus, the test should be repeated
several times to ensure consistent results. The test resistor will be connected
across the mains for the duration of each test. and will become very hot if
frequent tests are made. Some testers will then 'lock out' to prevent further
testing until the resistor temperature falls to a safe value.
The earth fault
loop impedance measured as described will be for installation cables at ambient
temperature, unless the circuit concerned has been in use immediately before the
test, when it will be the impedance at normal operating temperature. Under
normal operating conditions, cable temperature will rise, and so will the
resistive component of the impedance. This effect is difficult to calculate, and
a practical alternative is to ensure that the measured values of earth fault
loop impedance do not exceed three quarters of the maximum values shown in {Tables 5.1, 5.2
or 5.4} as appropriate.
A circuit protected by
an RCD will need special attention, because the earth-fault loop test will draw
current from the phase which returns through the protective system. This will
cause an RCD) to trip. Therefore, any RCDs must be bypassed by short circuiting
connections before earth-fault loop tests are carried out. It is, of course, of
the greatest importance to ensure that such connections are removed after
testing. One manufacturer supplies a patented loop tester which does not require
RCDs to be short circuited and which will not cause them to trip
when the earth-fault loop test is made. Some instruments limit the test current to 15
mA so as not to trip RCDs with ratings of 30 mA and above. Whilst such tests may
often be useful, they do not test the integrity of the system under fault
current conditions.
When loop testing at lighting units controlled by passive
infrared detectors (PIRs), there may he damage to the associated electronic
switches unless they are short-circuited before testing.
An alternative to the use of a dedicated earth-fault loop
impedance tester is to measure the combined resistance of the phase and
protective conductors from the incoming position to the point for which
earth-fault loop impedance is required (this is R1 + R2 - ) and to add to it the external
earth-fault loop impedance (Ze) which can be obtained from the electricity
supplier. All earth-fault loop impedance test results should be carefully
compared with the data in [Tables 41B and 41D], adjusted to allow for ambient
temperature, or with figures provided by
the designer. To ensure that ambient temperature is taken into account, the
results should never exceed three quarters of the values given in [Tables 41B
and 41D].
8.6.3 - Testing residual current devices (RCDs)
Residual current devices should comply with BS 4293 and are
described in (5.9),
from which it will be seen that they are provided with a built-in self test
system which is intended to be operated regularly by the user. BS 7671 requires
that correct operation of this test facility should be checked, and that other
tests are also carried out. The time taken for the device to operate must be
measured, so the old type of 'go, no-go' tester is no longer adequate. {8.7.1} gives test
instrument requirements.
RCD tests are carried out with a special tester which is
connected between phase and protective conductors on the load side of the RCD
after disconnecting the load {Fig 8.19}. A precisely measured current for a
carefully timed period is drawn from the phase and returns via the earth, thus
tripping the device. The tester measures and displays the exact time taken for
the circuit to be opened. This time is very short, in most cases being between
10 and 20 ms, although it can be much longer, especially for S-types which have
delayed operation
Fig 8.19 - Connections for an RCD
tester
1. - General
purpose non-delayed RCDs
This is a general purpose
type of RCD which is intended to operate very quickly at its rated current.
Three tests are required:
a) - 50% of the rated tripping current applied for
2 s should not trip the device,
b) - 100% of
rated tripping current, which should not he applied for more than 2 s, must
cause the device to trip within 200 ms (0.2 s), and
c) - where the
device is intended to provide supplementary protection against direct contact, a
test current of 150 mA, applied for no more than 50 ms, should cause the device
to operate within 40 ms.
2. - Time-delayed RCDs
In {5.9.2} we discussed the
need for discrimination between RCDs. This type is deliberately delayed in its
operation to make sure that other devices which are connected downstream of it
will operate more quickly. A 3:1 discrimination ratio is required between two
RCDs which are connected in series, and this must be verified before testing. It
means that the delayed RCD must have an operating current at least three times
that of the non-delayed type. For example, to discriminate properly with a 30 mA
device, a second connected on the supply side would need to have an operating
current of at least 90 mA (in practice, a 100 mA RCD is likely to be
used).
The test for the
time-delayed RCD consists of applying 100% of the normal rated current, when the
device should trip within the time range of:
For example, an RCD with a rated tripping time of
300 ms should trip within a time range of:
An RCD tester is an electronic device which draws current
from the supply for its operation. This current is usually of the order of a few
milliamperes which is taken from the phase and neutral of the supply under test,
and will have no effect on the measurement of single-phase systems. However, if
a three-wire three-phase system (there is no neutral with this supply) is being
tested, the tester must be connected to a neutral conductor to provide the power
it needs for operation. Thus, its operating current will flow through a line
conductor and return through the neutral, giving a basic imbalance. A 'no-trip'
test must also be carried out, during
Fig 8.20 - RCD tester connected for
use
which the RCD must not operate when 50% of the rated tripping
current is applied for 2 s. The extra current to power the tester, which adds to
the test current, may then cause operation. It is necessary in this case to
obtain from the RCD manufacturer the value of this current and to take it into
account before failing a device on the 50% test.
The RCD tester is connected to the device to be tested by
plugging it into a suitable socket outlet (see {Fig 8.20}) or by connecting to
phase and neutral with special leads obtainable from the instrument
supplier.
| (150 + 200) ms =
350 ms and |
| (300+200) ms =
500 ms |
| 50% of rated time delay plus 200 ms, and |
| 100% of rated time delay plus 200
ms. |
|
|
|
The electrical tests. |
|
|
The electrical tests
8.4.1 - Protective conductor continuity
All protective and bonding conductors must be tested to
ensure that they are electrically safe and correctly connected. Provided that the supply is not yet connected, it is
permissible to disconnect the protective and equipotential conductors from the
main earthing terminal to carry out testing. Where the mains supply is
connected, as will be the case for periodic testing, the protective and
equipotential conductors must not be disconnected because if a fault occurs
these conductors may rise to a high potential above earth. In this case, an
earth-fault loop tester can be used to verify the integrity of the protective
system.
Where earth-fault loop impedance measurement of the
installation is carried out, this will remove the need for protective conductor
tests because that conductor forms part of the loop. However, the loop test
cannot be carried out until the supply is connected, so testing of the
protective system is necessary before supply connection, because connection of
the supply to an installation with a faulty protective system could lead to
danger.
There are three methods for measurement of the resistance of
the protective conductor.
1. - Using the neutral conductor as a return
lead
A temporary link is made at the distribution
board between neutral and protective conductor systems. Don't forget to remove
the link after testing. The low resistance tester is then connected to the earth
and neutral of the point from which the measurement is taken (see {Fig 8.2}).
This gives the combined resistance of the protective and neutral conductors back
to the distribution board. Then
| where |
| Rp - is the
resistance of the protective conductor |
| R - is the
resistance reading taken |
| An - is the cross-sectional area of the neutral
conductor |
| Ap - is the cross-sectional area of the protective
conductor. |
Note that the instrument reading taken in this case is the
value of the resistance R1 + R2 calculated from This method is
only valid if both conductors have the same length and both are copper; in most
cases where steel conduit or trunking is not used as the protective conductor,
the test will give correct results.
Fig 8.2 - Protective conductor continuity
test using the
neutral conductor as the return
lead
2. - Using a long return
lead
This time a long lead is used which will
stretch from the main earthing terminal to every point of the
installation.
First, connect the two ends of this lead to the
instrument to measure its resistance. Make a note of the value, and then connect
one end of the lead to the main earthing terminal and the other end to one of
the meter terminals.
Second, take the meter with its long lead still connected to
the point from which continuity measurement is required, and connect the second
meter terminal to the protective conductor at that point.
The
reading then taken will be the combined resistance of the long lead and the
protective conductor, so the protective conductor value can be found by
subtracting the lead resistance from the reading.
| Rp = R - RL |
| where |
| Rp - is the
resistance of the protective conductor |
| R - is the resistance reading
taken |
| RL - is the resistance of the long
lead |
Some modem electronic resistance meters
have a facility for storing the lead resistance at the touch of a button, and
for subtracting it at a further touch.
3. - Where ferrous material forms all or part of
the protective conductor
There are some cases where the protective
conductor is made up wholly or in part by conduit, trunking, steel wire armour,
and the like. The resistance of such materials will always be likely to rise
with age due to loose joints and the effects of corrosion. Three tests may be
carried out, those listed being of increasing severity as far as the
current-carrying capacity of the protective conductor is concerned. They
are:
1 - A standard ohmmeter test as indicated in 1 or 2
above. This is a low current test which may not show up poor contact effects in
the conductor. Following this test, the conductor should be inspected along its
length to note if there are any obvious points where problems could
occur.
2 - If it is felt by the inspector that there may be
reasons to question the soundness of the protective conductor, a phase-earth
loop impedance test should be carried out with the conductor in question forming
part of the loop.
3 - If it is still felt that the protective conductor
resistance is suspect, the high current test using 1.5 times the circuit design
current (with a maximum of 25 A) may be used (see {Fig 8.3}. The protective
circuit resistance together with that of the wander lead can be calculated
from:
| voltmeter reading (V) |
| ammeter reading
(A) |
Fig 8.3 - High-Current ac test of a
protective conductor
Subtracting wander lead resistance from the calculated value
will give the resistance of the protective system.
The resistance between
any extraneous conductive part and the main earthing terminal should be 0.05
Ohms or less; all supplementary bonds are also required to have the same
resistance.
8.4.2 - Ring final circuit continuity
The ring final circuit, feeding 13 A sockets, is extremely
widely used, both in domestic and in commercial or industrial situations. It is
very important that each of the three rings associated with each circuit (phase,
neutral and protective conductors) should be continuous and not broken. If this
happens, current will not be properly shared by the circuit conductors. {Fig
8.4} shows how this will happen. {Fig 8.4(a)} shows a ring circuit feeding ten
socket outlets, each of which is assumed to supply a load taking a current of 3
A. In simple terms, current is then shared between the conductors, so that each
could have a minimum current carrying capacity of 15 A. {Fig 8.4(b)} shows the
same ring circuit with the same loads, but broken between the ninth and tenth
sockets. It can be seen that now one cable will carry only 3 A whilst the other
(perhaps with a current rating of 20 A) will carry 27 A. The effect will occur
in any broken ring, whether simply one live conductor or both are
broken.
Fig 8.4 - illustrating the danger of a break
in a ring final circuit
a) unbroken ring with correct current
sharing
b) broken ring with incorrect current sharing
It is similarly important that there should be no 'bridge'
connection across the circuit. This would happen if, for example, two spurs from
different points of the ring were connected together as shown in {Fig
8.5}, and again could result in incorrect load sharing between the ring
conductors.
The tests of the ring final circuit will establish that
neither a broken nor a bridged ring has occurred. The following suggested test
is based on the Guidance Note on Inspection and Testing issued by the
IEE.
Fig 8.5 - A 'bridged' ring final
circuit
Test 1
This test confirms
that complete rings exist and that there are no breaks. To complete the test,
the two ends of the ring cable are disconnected at the distribution board. The
phase conductor of one side of the ring and the neutral from the other (P1 and
N2J are connected together, and a low resistance ohmmeter used to measure the
resistance between the remaining phase and the neutral (P2 and Ni). {Figure 8.6}
shows that this confirms the continuity of the live conductors. To check
the continuity of the circuit protective conductor, connect the phase and CPC of
different sides together (P1 and E2) and measure the resistance between phase
and CPC of the other side (P2 and El). The result of this test will be a
measurement of the resistance of live and protective conductors round the ring,
and if divided by four gives (Ri + R2) which will conform with the values
calculated from
Fig 8.6 - Test to confirm the continuity of a
ring final circuit
Test 2
This test will confirm
the absence of bridges in the ring circuit, see {Fig 8.7}. First, the phase
conductor of one side of the ring is connected to the neutral of the other (P1
and N2) and the remaining phase and neutral are also connected together (P2 -and
Ni). The resistance is then measured between phase and neutral contacts of each
socket on the ring. If the results of these measurements are all substantially
the same (within 0.05 Ohms), the absence of a bridge is confirmed. If the
readings are different, this will indicate the presence of a bridge or may be
due to incorrect connection of the ends of the ring. If they are connected P1 to
NI and P2 to N2 then readings will increase or reduce as successive measurements
round the ring are taken, as is the case where a bridge exists. Whilst this
misconnection is easily avoided when using sheathed cables, a mistake can be
made very easily if the system consists of single-core cables in conduit. It may
be of interest to note that the resistance reading between phase and neutral
outlets at each socket should be one quarter of the phase/neutral reading of
Test 1.
Measurements are also taken at each socket on the ring
between the phase and the protective conductor with the temporary connection
made at the origin of the ring between P1 to E2 and between P2 to El.
Substantially similar results will indicate the absence of
bridges.
Fig 8.7 - Test to confirm the absence of
bridges in a ring final circuit
8.5.1 - Testing insulation resistance
A low resistance between phase and neutral conductors, or
from live conductors to earth, will result in a leakage current. This current
could cause deterioration of the insulation, as well as involving a waste of
energy which would increase the running costs of the installation. Thus, the
resistance between poles or to earth must never be less than half of one meg ohm
(0.5 M Ohms) for the usual supply voltages. In addition to the leakage current
due to insulation resistance, there is a further current leakage in the
reactance of the insulation, because it acts as the dielectric of a capacitor.
This current dissipates no energy and is not harmful, but we wish to measure the
resistance of the insulation, so a direct voltage is used to prevent reactance
from being included in the measurement. Insulation will sometimes have high
resistance when low potential differences apply across it, but will break down
and offer low resistance when a higher voltage is applied. For this reason, the
high levels of test voltage shown in {Table 8.8} are necessary.
Before commencing the test it is important
that:
1. - electronic equipment which could be damaged by
the application of the high test voltage should be disconnected. Included in
this category are electronic fluorescent starter switches, touch switches,
dimmer switches, power controllers, delay timers, switches associated with
passive infrared detectors (PIRs), RCDs with electronic operation etc. An
alternative to disconnection is to ensure that phase and neutral are connected
together before an insulation test is made between them and
earth.
2. - capacitors and indicator or pilot lamps must
be disconnected or an inaccurate test reading will result.
|
Table 8.8 - Required test voltages and minimum
resistance
|
Nominal circuit voltage
|
Test voltage
(V)
|
Minimum insulation resistance
(M
Ohms)
|
| Extra-low voltage circuits supplied from a safety
transformer |
250
|
0.25
|
| Up to 500 V except for above |
500
|
0.5
|
| Above 500 V up to 1000 V |
1000
|
1.0
|
| The insulation resistance tester must be capable of
maintaining the required voltage when providing a steady state of current of
1mA. |
Where any equipment is disconnected for testing
purposes, it must be subjected to its own insulation test, using a voltage which
is not likely to result in damage. The result must conform with that specified
in the British Standard concerned, or be at least 0.5 M Ohms if there is no
Standard.
The test to earth {Fig 8.10} must be carried out on the
complete installation with the main switch off, with phase and neutral connected
together, with lamps and other equipment disconnected, but with fuses in,
circuit breakers closed and all circuit switches closed. Where two-way switching
is wired, only one of the two strapper wires will be tested. To test the other,
both two-way switches should be
Fig 8.11 - Insulation tests between
poles
operated and the system retested. If desired, the
installation can be tested as a whole, when a value of at least 0.5 M Ohms
should be achieved, see {Fig 8.10}. In the case of a very large installation
where there are many earth paths in parallel, the reading would be expected to
be lower. If this happens, the installation should be subdivided and retested,
when each part must meet the minimum requirement.
The tests to earth {Fig 8.10} and between poles {Fig 8.11}
must be carried Out as indicated, with a minimum acceptable value for each test
of 0.5 M Ohms. However, where a reading of less than 2 M Ohms is recorded for an
individual circuit, (the minimum value required by the Health and Safety
Executive), there is the possibility of defective insulation, and remedial work
may be necessary. A test result of 2 M Ohms may sometimes be unsatisfactory. If
such a reading is the result of a re-test, it is necessary to consult the data
from previous tests to identify deterioration. A visual inspection of cables to
determine their condition is necessary during periodic tests; perished
insulation may not always give low insulation readings
As indicated above, tests on SELV and PELV circuits are
carried out at 250 V. However tests between these circuits and the live
conductors of other circuits must be made at 500 V. Tests to earth for PELV
circuits are at 250 V, whilst FELV circuits are tested as LV circuits at 500
V. Readings of less than 5 M will
require further investigation.
8.5.2 - Tests of non-conducting floors and
walls
Where protection against indirect contact is provided by a
non-conducting location, the following requirements apply.
1. - there must be no protective
conductors
2. - if socket outlets are used they must not have an
earthing contact
3. - it should be impossible for any person to touch
two exposed conductive parts at the same
time
4. - floors and walls must be
insulating.
To test this last item and so to make sure that the floors
and walls are non-conducting, their insulation has to be tested.
The requirements are shown in {Fig 8.12}, the electrodes used
for making contact
Fig 8.12 - Insulation test of floors and
walls for non-conducting location
with floors and walls being a special type which are pressed
onto the surface with a force of not less than 750 N (77 kg or 169 lb) for
floors or 250 N (26 kg or 56 lb) for walls. The resulting insulation resistance
of not less than three points on each surface, one of which must be between 1 m
and 1.2 m from an extraneous conductive part (if there is one), measured at 500
V, must not be less than 0.5 MOhms. Attention is drawn to the natural reduction
in the insulation resistance of a surface as humidity increases. Where
insulation is applied to an extraneous conductive part to provide a
non-conducting location, this insulation must be tested with an alternating p.d.
of 2 kV. In normal use, the leakage current should not exceed I mA.
8.5.3 - Tests of barriers and enclosures
Throughout the Regulations reference is made to the use of
barriers and enclosures to prevent contact with live parts (direct contact). If
manufactured equipment's comply with the British Standards concerned, they will
not need further testing, but where barriers and enclosures have been provided
during erection of the installation, they must be tested. The two most
common tests are for:
1. - IP2X - no contact can be made with a probe 12 mm
in diameter and 80 mm long
- in other words, a human finger
2. - IP4X - no contact can be made with a rod of
diameter 1 mm.
8.5.4 - Tests for electrical separation of
circuits
This section is concerned with tests necessary to ensure the
safety of separated extra-low voltage (SELV), protective extra-low voltage
(PELV) and functional extra-low voltage (FELV) circuits. In general,
the requirement is a thorough inspection to make sure that the source of low
voltage (most usually a safety isolating transformer) complies in all respects
with the British Standard concerned, followed by an insulation test between the
extra-low voltage and low voltage systems. The test is unusual in that a 500 V
dc supply (from an insulation resistance tester) must be applied between the
systems for one minute, after which the insulation resistance must not be less
than 5 MOhms for SELV or PELV systems, or 0.5 MOhms for FELV systems. A further
test at 3750 V dc for one minute is passed if no flashover occurs. This test in
particular can be dangerous, and special care should be taken.
For SELV and FELV circuits, additional inspection must ensure
that the low voltage requirements (not exceeding 50 V ac or 120 V dc) are met.
If the voltage exceeds 25 V ac or 70 V dc (60 V ripple-free), barriers and
enclosures must be tested to IP2X and a 500 V dc
insulation test applied for one minute between the live conductors and metal
foil wrapped round the insulation should produce a result of at least 0.5
MOhms
When insulation testing on electrically isolated circuits or
on equipment which might be damaged by the test voltage, phase and neutral must
be connected together and the test applied between them and earth.
|
|
|
Domestic electrical testing |
|
|
Domestic Electrical Safety Testing to BS7671 (16th Editition)
There is little point in setting up Regulations to control
the way in which electrical installations are designed and installed if it is
not verified that they have been followed. For example, the protection of
installation users against the danger of fatal electric shock due to indirect
contact is usually the low impedance of the earth-fault loop; unless this
impedance is correctly measured. this safety cannot be confirmed. in this case
the test cannot be carried out during installation, because part of the loop is
made up of the supply system which is not connected until work is complete.
In the event of an open circuit in a protective conductor,
the whole of the earthed system could become live during the earth-fault loop
test. The correct sequence of testing would prevent such a danger, but the tester must always
be aware of the hazards applying to himself and to others due to his activities.
Testing routines must take account of the dangers and be arranged to prevent
them. Prominent notices should be displayed to indicate that no attempt should
be made to use the installation whilst testing is in progress.
The precautions to be taken by the tester should include the
following:
1. - make sure
that all safety precautions are observed
2. - have a clear understanding of the installation,
how it is designed and how it has been installed
3. - make sure
that the instruments to be used for the tests are to the necessary standards (BS
4743 and BS 5458) and have been recently recalibrated to ensure their
accuracy
4. - check that the test leads to be used are in good
order, with no cracked or broken insulation or connectors, and are fused where
necessary to comply with the Health and Safety Executive Guidance Note GS38
5. - be aware of the dangers associated with the use
of high voltages for insulation testing. For example, cables or capacitors
connected in a circuit which has been insulation tested may have become charged
to a high potential and may hold it for a significant time.
8.2.1 - Notices and other identification
The installation tester, as well as the user, must have no
difficulty in identifying circuits, fuses, circuit breakers, etc. Re must make
sure that the installation is properly equipped with labels and notices, which
should include:
I. - Labels for all fuses and circuit breakers to
indicate their ratings and the circuits protected
2. - Indication of the purpose of main switches
and isolators
3. - A diagram or chart at the mains position showing
the number of points and the size and type of
cables for each circuit, the method of providing protection from direct contact
and details of any circuit in which there is
equipment such as passive infra-red detectors or electronic fluorescent
starters vulnerable to the high voltage used for insulation
testing.
4. - Warning of the presence of voltages exceeding 250
V on an equipment or enclosure where such a voltage would not normally be
expected.
5. - Warning that voltage exceeding 250 V is present
between separate pieces of equipment
which are within arm's
reach
6. - A notice situated at the main intake position to
draw attention to the need for periodic testing
7. - A warning of the danger of disconnecting
earth wires at the point of connection of:
a). - the earthing conductor to the earth electrode
b). - the main earth terminal, where separate from main switchgear
c). -
bonding conductors to extraneous conductive parts The notice should
read Safety electrical connection - do not remove
8. - A notice to indicate the need for periodic
testing of an RCD.
9. - A notice
for caravans so as to draw attention to the connection and disconnection
procedure as indicated in
10. - Warning of the need for operation of two
isolation devices to make a piece of equipment safe to work on where this applies
11. - A schedule at each distribution board listing
the items to be disconnected (such as semiconductors) so that they will not be
damaged by testing.
12. - A drawing which shows clearly the exact position
of all runs of buried cables.
8.3.1 - Why is correct sequence important?
Testing can be hazardous, both to the tester and to others
who are within the area of the installation during the test. The danger is
compounded if tests are not carried out in the correct sequence.
For example, it is of great importance that the continuity,
and hence the effectiveness, of protective conductors is confirmed before the
insulation resistance test is carried out. The high voltage used for insulation
testing could appear on all extraneous metalwork associated with the
installation in the event of an open-circuit protective conductor if insulation
resistance is very low.
Again, an earth-fault loop impedance test cannot be conducted
before an installation is connected to the supply, and the danger associated
with such a connection before verifying polarity, protective system
effectiveness and insulation resistance will be obvious.
Any test which fails to produce an acceptable result must be
repeated after remedial action has been taken. Any other tests, whose results
may have been influenced by the fault concerned must also be repeated.
8.3.2 - Correct testing sequence
Some tests will be carried out before the supply is
connected, whilst others cannot be performed until the installation is
energised. {Table 8.5} shows the correct sequence of testing to reduce the
possibility of accidents to the minimum.
|
Table 8.5 - Correct sequence for safe
testing
|
|
BEFORE CONNECTION OF THE
SUPPLY
|
|
1
|
Continuity of protective
conductors |
|
2
|
Main and supplementary bonding
continuity |
|
3
|
Continuity of ring final circuit
conductors |
|
4
|
Insulation resistance |
|
5
|
Site applied insulation |
|
6
|
Protection by separation |
|
7
|
Protection by barriers and
enclosures |
|
8
|
Insulation of non-conducting floors and
walls |
|
9
|
Polarity |
|
10
|
Earth electrode resistance if an earth electrode
resistance tester is used |
|
WITH THE SUPPLY
CONNECTED
|
|
11
|
Earth electrode resistance if an earth-fault loop
tester or the ammeter and voltmeter method are used |
|
12
|
Confirm correct polarity |
|
13
|
Earth-fault loop impedance |
|
14
|
Correct operation of residual current
devices |
|
15
|
Correct operation of switches and isolators |
|
|
| |
|